ROSATOM subsidiary awards contract for construction of BREST-OD-300 fast reactor facility and power unit

ROSATOM subsidiary awards contract for construction of BREST-OD-300 fast reactor facility and power unit

Seversk, Tomsk region, December 9 - Neftegaz.RU. Siberian Chemical Plant (a subsidiary of TVEL) has signed the contract with Concern Titan-2 engineering company for construction and installation works within the project of BREST-OD-300 lead-cooled fast neutron reactor facility.

The total contract value is 26.3 billion RUB. The contractor will accomplish construction of reactor hall, turbine hall and related infrastructure facilities of the power plant. The completion is scheduled till the end of 2026.

“Contracting for BREST-OD-300 reactor facility and power unit construction is the major long-anticipated milestone of “the Breakthrough” project implementation in 2019. After commencing the works for the fabrication/refabrication facility, we are moving further to construction of the key facility of PDEC which should become the prototype of the nuclear power of the future. Besides, construction and operation of PDEC facilities would create over 800 new jobs in Seversk,” commented Vitaly Khadeev, VP for Development of Closed Nuclear Fuel Cycle Technologies and Industrial Facilities at TVEL.

“Proryv” or “the Breakthrough” project targets creation of the new technology platform for the industry with closed nuclear fuel cycle, as well as tackling the issues of spent nuclear fuel and radioactive waste. One of the project inplementations is construction of the Pilot Demonstration Energy Complex with a lead-cooled BREST-OD-300 fast neutron reactor facility with an on-site closed nuclear fuel cycle.

A 300 MW plant powered by the innovative fast reactor is the key facility of the Pilot Demonstration Energy Complex (PDEC), which is in process of construction at the Siberian Chemical Plant, as a part of the strategic Russian nuclear project “Proryv” or “the Breakthrough”. In addition to the power unit, PDEC will include an on-site closed nuclear fuel cycle with a facility for fabrication/re-fabrication of mixed nitride uranium-plutonium nuclear fuel, as well as a spent fuel reprocessing facility.

Follow us on Facebook
Advertising at neftegaz.ru

Subscribe to our newsletter

of the best materials Neftegaz.RU

* Incorrect E-Mail Address

By clicking the "Subscribe" button I accept the "Agreement on the processing of personal data"


Advertising at neftegaz.ru