Comprehensive logistics scheme developed for the modernisation of the Gazprom Neft Omsk Refinery

Transportation of major new equipment to the Gazprom Neft Omsk Refinery has required the development of a comprehensive logistics scheme.

Comprehensive logistics scheme developed for the modernisation of the Gazprom Neft Omsk Refinery


Gazprom Neft reported on August 15, 2016, that transportation of major new equipment to the company´s Omsk Refinery has required the development of a comprehensive logistics scheme.

Equipment intended for the construction of new facilities (part of the full-scale modernisation of the Omsk Refinery, and weighing about 6,000 tonnes in total) is being transported to Omsk in stages, by sea and river vessels.

The equipment, produced at the JSC Volgogradneftemash plant, was transported along the Volga, through the Rybinsk Reservoir, and through Lake Onezhskoye and Lake Ladoga.
Components from the JSC Volgogradneftemash and Izhorskiye Zavodi plants are currently being transported through the Neva to the coast of the Gulf of Finland. The 2nd leg of the route will run through the Baltic, North and Norwegian Seas, as well as part of the Northern Sea Route, to the Gulf of Ob. The 3rd (and final) stage will involve oversized cargo being transported from Novy Port to Omsk via the Ob and Irtysh rivers.

The total distance covered in transporting the equipment will be more than 9,000 kilometres. Delivery of the equipment to the Omsk Refinery is expected in October 2016.


Follow us on Google News
Advertising at neftegaz.ru

Subscribe to our newsletter

of the best materials Neftegaz.RU

* Incorrect E-Mail Address

By clicking the "Subscribe" button I accept the "Agreement on the processing of personal data"


Advertising at neftegaz.ru